Adding a custom due date to a package
Adding a custom due date to a package
Package due dates override a project's due date (for that package).
You can set a date that's earlier than the project's due date, but not later.
You can add a due date to a package in two ways.
You can set a date that's earlier than the project's due date, but not later.
You can add a due date to a package in two ways.
Option 1: When setting up a new project and inviting subbies
When you're at step 5 (Invitations) of setting up a new project, there is now a Due date field before [Next Trade].
By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.
Option 2: After you've set up the project
Start by going to the Invites & Responses page for the project (for example, via the Dashboard).
In the [Quick Actions] menu, choose Invite Multiple.
Just like in Option 1 above, there is a now a Due date field before [Next Trade].
By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.
You can only change a package's custom due date if you issue a new invitation.